The number of days needed in renovating a house varies inversely as the number of men working. It takes 6 days for 8 men to renovate the house. How many men are needed to complete the job in 4days? *​

Sagot :

Answer:

12 men

Step-by-step explanation:

6 days/ 8men=4 days/ x men

6(8)=4x

48=4x

divide both sides by 4

12=x

12 men are needed to complete the job in 4days